Creating a Maintenance Schedule

Create a maintenance schedule to prevent orders being placed for part of the network for a fixed period.

What happens when there are orders in the proposed maintenance schedule?

If a new maintenance schedule will overlap with existing orders, you are prompted to review a list of the affected orders. If you do not want to change the orders to avoid the maintenance schedule, you are warned of the overlap and are prompted to confirm that you want to proceed.

Note:

Orders that have already been planned can be modified by the Planner by editing the plan.

To create a maintenance schedule:

  1. Click Maintenance Schedules to open the Maintenance Schedules module.
  2. Click Add to create a new maintenance schedule.
  3. Enter the following details:

    FieldDescription

    Area

    Select the part of the network for which the schedule will apply. You can select either areas or groups.

    Begin/End Date

    Enter the schedule start and end dates

    Reason

    Add an optional description of the maintenance period.

  4. Click Save to save your changes.



Help for SPM, version 3.4. Topic updated: 30 May 2018. Help published: 14 June 2019